At 20 °C, 45% RH is about a 7.7 °C dew point, within reach of a cooling coil on roughly 5 °C chilled water; 30% RH is about 1.9 °C and points to desiccant dehumidification. EU GMP gives no RH value, so derive the limit from product moisture data and exposure time before sizing plant.
An HVAC energy saving is only as good as its baseline. Hold room limits, weather file, production and cleaning schedules and airflow justification identical in both models, and define the baseline system in writing, for example with ASHRAE 90.1 Appendix G, before quoting any percentage.
After a cold spell in northern Viet Nam, warm humid air arrives while floors and stored goods are still cold. Air at 20 °C and 90% RH has a dew point of about 18.3 °C, so a 15 °C slab gets wet. Extra ventilation adds more of the same air; dry the air or warm the surface.
A 1,000 m² fab bay with FFUs over 90% of its ceiling holds about 1,250 units of 1,200 × 600 mm. After handover each is a motor on the BMS, and the design documents should group the units by tool and zone so the fault logic can tell a work order from an alarm.
With the motor in the airstream, fan power becomes heat: about 2.1 K at 1,500 Pa and 60% efficiency, roughly 14 kW on a 20,000 m³/h unit. After the coil it reaches the room; counted twice, it oversizes a chilled-water coil that then dehumidifies poorly at part load.
Taking over HVAC maintenance in a running GMP plant starts with four outputs in the first 90 days: a walk-down of every asset behind a GMP parameter, a criticality ranking, the calibration status of every BMS and EMS input, and ownership of open HVAC deviations and CAPAs.
Ho Chi Minh City outdoor air carries about 16 g/kg of water on the hottest afternoon and about 21 g/kg at peak dew point. A fresh-air coil sized on the hot condition falls short in the wet season, and after tender the fix is a variation. Settle it while the design is still moving.
At 16 fins per inch a cooling coil has a fin pitch of about 1.6 mm, and a dehumidifying coil in the tropics runs wet most of the year. Water bridges the gap, pressure drop rises, droplets carry over and film grows. At 10 fins per inch the pitch is about 2.5 mm, at the cost of a larger coil.
A recovery test with a 20-minute limit, traced to a 15-minute URS requirement, passes and leaves the requirement unproven. Reading a trace matrix from each test back to its requirement finds these weak links and orphan tests. Pick three signed results at random and trace them back.
Every 1,000 m³/h of outdoor air at 20 g/kg brings about 24 kg/h of water into a dry room plant, and the make-up airflow is set by process exhaust. A line exhausting 5,000 m³/h means about 120 kg/h. Firm exhaust flows come first.
At 21 °C and 50% RH, a sensor reading 0.5 K warm reports humidity about 1.5% RH low, most of a ±2% RH band. Wall sensors near doors read their corner, return-duct sensors lag, slow sensors make the loop hunt and drift takes the rest. Sensor position is a design decision.
A 10,000 m³/h fan at 1,500 Pa and 0.6 overall efficiency draws about 6.9 kW, around 61 MWh a year in a cleanroom. Every 100 Pa removed at design stage saves about 0.46 kW for the life of the plant. A pressure budget per AHU in the design basis is where it starts.