Clean AHU cooling coils from the leaving face with low-pressure water or steam and an approved, fully rinsed detergent, after checking the drain. Take the frequency from the coil's pressure drop trend against a commissioning baseline, and record the method, detergent batch, before and after readings and photos of both faces.
Primary-secondary pumping is simple to control, but reverse flow in the decoupler sends warmer water to the coil that sets room dew point. Variable-primary saves pump energy but has to hold each chiller's minimum flow while chillers stage. For a GMP plant, choose the scheme your controls contractor can commission and prove.
A control panel FAT is the last time every wire is reachable and the drawings are on the table. Use it for IEC 61439-1 routine verification, point-to-point I/O, interlocks, alarm texts and approved software versions. The same fault found during site loop checks costs a day instead of minutes.
On an equipment-only AHU purchase, write the EN 1886 casing leakage class and F9 filter bypass into the order, witness the leakage test on the built unit at FAT, check the selection against the project airflow schedule, and require the equipment file compiled during production so IQ starts complete.
Standing water under a cooling coil is the classic growth source in an AHU. A hygienic unit adds a drain pan that empties completely, smooth closed inner surfaces, full-size access doors, filter bypass class F9 to EN 1886, removable parts and a complete equipment file. Write each into the specification as a FAT check.
Record the as-found reading before any adjustment. A room pressure transmitter reading 2 Pa high on a 10 Pa limit can hide months at 9 Pa. An out-of-tolerance as-found result triggers an impact assessment on every record since the last good calibration.
EPC moves cost and schedule risk to one contractor at a fixed price; compliance risk stays with the owner under any contract form. If the tender never named who writes and executes the DQ, IQ, OQ and PQ protocols, the lump sum did not include them. Owners who cannot define that yet are often better served by EPCM.
An excursion record that ends with "returned to range" describes the logger trace and leaves the product question open. Assess duration and peak from the load logger, stability data for that product, affected batches, root cause, CAPA and a signed QA decision. In Viet Nam's climate, a 15–25 °C route also needs active cooling.
"Type-tested" is IEC 60439 wording. IEC 61439-1 separates design verification (Clause 10), which proves the assembly system once, from routine verification (Clause 11), which checks every panel built. At FAT a buyer should receive the design verification report and a routine record tied to the panel serial number.
Owners holding a finished design need someone to run the build against it, while the design stays with the designer of record. Design gaps are best listed at the first stage gate in five columns: the drawing, what is missing, the activity blocked, who closes it, and a date taken from the blocked activity's schedule.
Annex 1 (2022) expects an aseptic process simulation to imitate routine processing with worst-case conditions. An APS run right after a filter change and rebalance tests a different process. Schedule maintenance away from APS runs and record the HVAC state for each run like the interventions.
A mechanical completion certificate records static checks: built as drawn, pressure and leakage tested, cables tested, punch items sorted. Starting fans needs a separate ready-for-commissioning certificate, signed by the commissioning lead, covering flushing, cleanliness, calibration, interlocks and approved procedures, so the rooms are walked before first start.