Skip to content

Newsroom

News & Insights

Company news from Humiley Group INC and technical notes on cleanroom HVAC, GMP validation, semiconductor environments and energy-storage engineering.

  • 780 articles

Everything

From the Humiley newsroom

102 articles tagged #BMSEMS.

Keep the BMS outside the EMS validation boundary

When the BMS and the validated EMS share one platform, the validation boundary takes in the control logic and every setpoint change becomes change control. An EMS with its own sensors, database and QA alarms under Part 11 and Annex 11 allows the BMS to be managed under good engineering practice.

InsightRead

Annex 11 and the BMS-to-EMS link

The 2011 text of Annex 11 (clause 5) says systems that exchange data electronically should include built-in checks for correct and secure entry and processing. On a BMS-to-EMS link we read that as status flags, a communication watchdog, end-to-end checks of units and time stamps, and a loss-of-communication test in the qualification.

InsightRead

High room humidity: five checks, in order

Reheat lowers the RH reading and leaves the water in the air. Before adding it, check outdoor dew point against design, chilled water temperature and valve position, and coil leaving dew point. Then look at reheat and the room sensor, and finally at doors, infiltration and new moisture sources.

InsightRead

A supplier's standard IQ/OQ protocol was written for the standard machine, before your URS existed. EU GMP Annex 15 (2015) says site personnel should confirm its suitability before approval, and that vendor protocols may be supplemented. Trace each URS line to a test, then write a short supplementary protocol for the lines left uncovered.

InsightRead

Replacing an EMS: migrate the data before the old system goes

When an environmental monitoring system is replaced, years of records move with it or become unreadable. List the records and retention periods, specify what moves, verify a trial migration, migrate under change control and keep the old data readable. The 2011 text of Annex 11 says validation should include checks on value and meaning.

InsightRead

Does the EMS alarm reach a person?

An alarm that appears on a screen in an empty control room has not been delivered. Test the notification chain: every route delivers, the time from event to receipt is measured, escalation works when nobody acknowledges, the out-of-hours list is current, and a failed message service raises its own alarm.

InsightRead

A variable-speed chilled-water pump that holds design head across its own headers hardly slows down. In a 300 kPa example, a sensor at the index coil brings the head down to 120 kPa at half flow. The US energy standard ASHRAE 90.1 requires measurement at or near the most remote heat exchanger and, with DDC, setpoint reset from valve positions.

InsightRead

A nightly backup means up to 24 hours of data can be lost. That is a recovery point objective, RPO, whether or not anyone chose it. The recovery time objective, RTO, is how long the system may stay down. Both should be written down, signed by QA and proven with a timed restore test.

InsightRead

Operators run the plant from BMS graphics, so errors there become operating errors. Check each screen for five things: every value has a unit and a tag, the setpoint sits beside the actual value, alarm colours follow one convention, stale values look different from live ones, and room names match the room codes.

InsightRead

A chilled water coil piped in parallel flow still cools, so the error often survives commissioning. It shows as a valve at 100%, return water colder than design and an off-coil temperature that misses setpoint. Mark inlet and outlet at the factory, check at FAT, and look again before the insulation goes on.

InsightRead