A new AHU started during construction loads its coil, drain pan and final filters with site dust that does not vacuum off wet fins. Clean the casing before power-on, seal duct openings, run on temporary pre-filters, fit final filters after the final clean and record it for IQ.
Duct leakage, cascade balance, controls tuning and recovery can only be measured once an AHU is connected on site. A FAT can still speed up those tests by recording clean filter and coil pressure drops, the casing leakage result, fan airflow at design static and the panel software version with its I/O list.
The sequence of operation decides what a cleanroom does on restart, on a trip and in a power cut. QA usually meets it at OQ, when every change costs a software revision and a retest. Walk it line by line with QA and maintenance before panels are built: start order, trips, alarm delays and fail positions.
A catalogue AHU suits an office zone or a like-for-like swap. Where humidity is specified it needs checking: a room at 20 °C and 45% RH has a dew point of about 7.7 °C, and a range coil can meet total kW yet leave the air wetter. Ask for leaving-air dew point at the site's peak condition.
Replacing an AHU in a running facility starts with as-found readings: terminal airflows, pressures across the cascade, temperature and RH. They are the balancing target for the new unit and the evidence that the qualified state returned. Decide with QA beforehand whether to balance to design or to as-found.
A 900 mm cleanroom door with a 5 mm undercut leaks about 50 m³/h at 15 Pa, and about 100 m³/h at 10 mm. Door gaps set how much offset air holds a 10–15 Pa cascade. Specify door leakage as a number at a stated pressure, with the test, and check it before installation.
Heat tint is removed by pickling or mechanical cleaning, then passivation restores the oxide layer, and a treated part looks like an untreated one. The only proof is the record made at the time: procedure, chemical, contact time, date, operator and check. Collected during production, it means IQ starts from a complete file.
On positive-pressure AHU sections an outward-opening door is pushed off its gasket while the fan runs, so those doors should open inward and doors on negative sections outward. Where a positive-side door must open outward, fit a two-stage safety latch. Mark swing and latch type on the GA drawing, section by section.
Near the sea or heavy industry, condensate turns a copper-tube, aluminium-fin coil into a galvanic cell and the fin bond fails first. Coatings applied after assembly cover the cut edges that pre-coated fin stock leaves bare and the collars where its coating cracks. Select the coil with the maker's correction factor and ask for the salt-spray report.
In a draw-through AHU the coil section runs under suction. A trap seal shallower than that suction, about 51 mm of water column at 500 Pa, draws air in through the drain and floods the pan. Checking seal depth, fall and access on the walk-down avoids an OQ deviation.
Score the technical envelope of a cleanroom HVAC tender and sign it off before any price is opened. Issue the scoring sheet with the tender: mandatory items pass or fail, the rest weighted, for example 40% technical depth and 20% each for documentation, delivery and service. Score every listed deviation.
AHUs bought in several tenders arrive with many motor frames, belt sections and filter sizes, and the spares list grows to match. A standardization schedule in the AHU datasheets before tender, covering IEC motor frames, standard filter faces, one sensor make and common belts, keeps the store small and repairs fast.