EN 1886 class L2 allows an AHU casing 0.44 l/s per m² of leakage at −400 Pa. On a witnessed FAT, casing leakage, fan airflow at design static pressure, filter bypass and the control panel are checked against the approved specification, and both engineers sign the sheet that goes into the equipment file.
New slabs, screeds and plaster release water into the room for weeks after the HVAC starts. Tuning controls or running OQ humidity tests through that load measures the building drying out. Plan a dry-out period, trend RH and dew point daily, and start humidity OQ once the trend flattens.
A cleanroom is qualified on its supply airflow: air change rate, recovery time and hood velocity. Controlling room pressure by trimming supply moves those numbers with every door opening. Holding supply constant and modulating extract or return keeps the qualified airflow and still holds the pressure cascade.
5,500 CFM at 250 Pa is about 9,345 m³/h, 6.6% short of a 10,000 m³/h schedule at 400 Pa, and a 20 air-change room gets about 18.7. The static pressure gap shows only on the fan curve, and speeding the fan up for 7% more air costs about 23% more fan power.
For the same excess airflow, room pressure differential varies with the inverse square of the leakage area. On a finished cleanroom that area hides in door gaps, ungasketed light fittings, open socket boxes, panel joints and penetrations. Compare measured excess air with the design allowance at commissioning.
Standing condensate in an AHU drain pan sits upstream of the final filters. ASHRAE 62.1 asks for a pan sloped at least 10 mm per metre toward the outlet so it drains completely. Check the slope with a level at FAT, prime the trap after long shutdowns and inspect the pan on a schedule.
Voltage distortion is harmonic current multiplied by source impedance. An EC fan wall draws the same harmonic current on grid or generator, but a transformer is typically 4–6% impedance and a generator's subtransient reactance typically 12–20%. Model both sources and set a distortion limit for the busbar on standby power.
EU GMP Annex 15 allows some FAT results to be used at IQ and OQ when transport and installation do not affect them. For an AHU that means listing what the trip can change, from fan alignment to software version, retesting those on site and referencing the rest.
Commissioning is good engineering practice owned by engineering; qualification is QA-approved evidence on critical aspects. ISPE Baseline Guide Volume 5 and ASTM E2500 let one test serve both, if it was identified in advance, run to an approved protocol and agreed with QA before it ran.
Air in a ceiling void has never passed a HEPA filter. If the void sits above room pressure, leaks bring it down past light frames and HEPA collars. Keep one void at or below the lowest room under it, seal duct joints, and measure room-to-void pressure at commissioning.
Record the as-found reading before any adjustment. A room pressure transmitter reading 2 Pa high on a 10 Pa limit can hide months at 9 Pa. An out-of-tolerance as-found result triggers an impact assessment on every record since the last good calibration.
A clash found on Tuesday and reported on Friday costs three days. Early in a career the pull is to hold the problem until you have the fix. At Humiley, Integrity means saying it the same day, because the honest date we give clients only helps if it arrives while there is time to act.