"Type-tested" is IEC 60439 wording. IEC 61439-1 separates design verification (Clause 10), which proves the assembly system once, from routine verification (Clause 11), which checks every panel built. At FAT a buyer should receive the design verification report and a routine record tied to the panel serial number.
Water needs about 2,450 kJ/kg to evaporate, so every kg/h leaving a mopped floor or wash bay adds about 0.68 kW of latent load. It arrives after production, when the cooling coil unloads. Treat the cleaning shift as its own dehumidification design case.
An AHU design copied from Ho Chi Minh City to a site near Hanoi can miss the heating coil and the humidifier. Use ASHRAE's heating dry-bulb column to size preheat, the humidification dew point column to size the humidifier, and the dehumidification columns for the cooling coil.
Steam that has not absorbed before it meets a filter, fan or sensor leaves them wet. Take the absorption distance from the maker at the unit's real air speed and load, keep wet-sensitive parts beyond it, fit a trapped stainless drain pan and access, and add a downstream high-limit sensor.
Owners holding a finished design need someone to run the build against it, while the design stays with the designer of record. Design gaps are best listed at the first stage gate in five columns: the drawing, what is missing, the activity blocked, who closes it, and a date taken from the blocked activity's schedule.
Grade A allows 3,520 particles ≥ 0.5 µm per m³ at rest and in operation, and continuous monitoring shows it held. That only works if the sampling head sits near the point of fill facing the airflow, on short tubing that does not lose the ≥ 5.0 µm particles Annex 1 also limits.
Hydrogen is flammable from about 4% by volume and pools in roof pockets that a ridge detector cannot see, so electrolyser roofs are detailed without pockets or each pocket is vented and detected, with alarms at 10% and 20–25% LFL. In battery rooms, rack-level off-gas sensing matters for what it switches.
EN 1822 classifies a filter at its rated airflow. Above it, pressure drop rises roughly in proportion to media velocity, diffusion capture falls and the most penetrating particle size shifts smaller. A filter classed H14 at nominal flow may not reach H14 efficiency at 120% of it.
At −60 °C dew point air holds about 0.007 g of water per kilogram, roughly 3,000 times less than outdoor air in southern Viet Nam. By a rough sum, 1 m³/h of leakage uses up around 4,000 m³/h of dry supply air, so the envelope, airlocks and occupancy belong in the dryer specification.
At LOD 300 a BIM element has size, shape and location; LOD 350 adds its interfaces with other systems: connections, supports and clearances. Clash detection before LOD 350 finds ducts in beams but misses hangers, flanges and maintenance access, which then surface on site.
On a 7.5 m rack, eye level is rarely the worst position. WHO mapping guidance expects loggers in three dimensions and at high-risk points: top racks under the roof, dock doors, cooling outlets and dead corners. The map then decides where the permanent monitoring probes belong.
Condensate leaving a fresh-air coil equals dry-air mass flow times the drop in humidity ratio. At 10,000 m³/h dried from 21 to 7 g/kg that is about 170 litres an hour. Timed at the trap on a humid day, a shortfall points at water temperature, flow or bypass.