A 12-months-from-commissioning or 18-months-from-delivery warranty, whichever ends first, shrinks when the building is late. An AHU delivered in March and started in November keeps only ten months of cover. Tie the start to commissioning, get storage instructions in writing, and keep the storage log that makes a claim possible.
An EU marketing authorisation can only be held by an applicant established in the EEA, so a manufacturer in Viet Nam needs an EEA partner, subsidiary or acquired authorisation before filing. The MAH decision shapes the dossier, the timeline and who controls the product on the EU market.
Grade D sets the particle limit and little else. In an OSD compression room the product is the contaminant, handled with a pressure sink and local exhaust; a semi-solids room has little dust but heat and water from vessels and washdown. Fill in the process loads on the room data sheet before copying any airflow.
IQ should start from a verified installation. Before a turnover package moves from construction to qualification it needs a marked boundary, every IQ-blocking punch item closed, commissioning and balancing results, walked-down as-builts, calibration certificates and the equipment file. If one is missing, the package goes back.
Grade B at rest is held to 3,520 particles ≥0.5 µm and 29 ≥5 µm per m³. Annex 1 (2022) defines at rest for GMP grades as HVAC running, main equipment installed and standing by, and no personnel, reached after a clean-up period of under 20 minutes as guidance. The protocol should record that condition.
Neither an EN 10204 3.1 nor a 3.2 helps if the heat number is cut off a pipe before it is transferred. A 3.1 is validated by the manufacturer's independent inspector; a 3.2 adds a purchaser's or regulatory inspector at extra cost and lead time. Ask for 3.2 where the URS or a part's design code requires it.
IEC 61439-2 defines four forms of internal separation in a switchboard. Form 4 puts each feeder in its own compartment, so a failed AHU starter can be isolated while the other AHUs keep running; working beside live sections still follows site safety rules. Form 1 or 2 may force a section shutdown.
Primary-secondary pumping is simple to control, but reverse flow in the decoupler sends warmer water to the coil that sets room dew point. Variable-primary saves pump energy but has to hold each chiller's minimum flow while chillers stage. For a GMP plant, choose the scheme your controls contractor can commission and prove.
Cooling coils pay for dehumidification in chiller kWh; desiccant rotors mostly in reactivation heat, often above 100 °C for silica gel rotors. Compare them by listing the heat the site already has and its temperature. Very low dew points need desiccant regardless, and rotor outlet air still needs cooling.
On an equipment-only AHU purchase, write the EN 1886 casing leakage class and F9 filter bypass into the order, witness the leakage test on the built unit at FAT, check the selection against the project airflow schedule, and require the equipment file compiled during production so IQ starts complete.
AHU quotations show price, rarely running cost. EN 13053 velocity, fan power and heat recovery classes, declared at design airflow, make offers comparable on energy. Without them the tender is judged on capital cost and the pressure drop of a small casing shows up later in fan energy.
Steam that has not absorbed before it meets a filter, fan or sensor leaves them wet. Take the absorption distance from the maker at the unit's real air speed and load, keep wet-sensitive parts beyond it, fit a trapped stainless drain pan and access, and add a downstream high-limit sensor.