EU GMP Annex 15 allows some FAT results to be used at IQ and OQ when transport and installation do not affect them. For an AHU that means listing what the trip can change, from fan alignment to software version, retesting those on site and referencing the rest.
The revised EU GMP Annex 1 has applied since 25 August 2023, with point 8.123 following in 2024. A site still planning its gap assessment is years behind. Most findings land in the CCS, for example a pressure alarm delay set at commissioning that nobody can justify.
EU GMP Annex 11 periodic evaluation asks whether a computerized system is still valid and compliant. Most of the evidence already exists in change control, deviation and incident records and the upgrade history. Review first, then retest only the functions the review shows are affected.
Annex 1 (2022) asks for continuous Grade A particle monitoring, ≥ 0.5 and ≥ 5 µm, through all critical processing at no less than 28 L/min. That decides where the probe sits, how short the sample tube must be, and that the counter clock matches the batch record. Fix it before the barrier is ordered.
EU GMP Annex 15 section 3 asks for design compliance with GMP to be demonstrated and documented, with URS requirements verified during DQ. Meeting minutes rarely do that. A DQ report traces every URS line to a drawing, calculation or datasheet at a stated revision, with a verdict and a signature.
A plant outside the EU earns an EU GMP certificate after an inspection by an EEA competent authority, usually triggered by the EU importer or MAH. Site Master File, inspection, graded deficiencies and a CAPA response come first; the certificate, or a non-compliance statement, then appears in EudraGMDP.
Moving a room pressure setpoint from 15 Pa to 12 Pa changes nothing physical and still changes a qualified parameter. Annex 15 section 11 and Annex 11 put it under change control: raise it, assess the cascade and the CCS, decide on retest, then edit. Lock qualified setpoints behind a controlled role.
FDA's 2004 aseptic guidance asks for at least 10–15 Pa between rooms of different classification; Annex 1 gives at least 10 Pa as guidance. Setting each cascade step at 15 Pa meets both. Holding it is harder: seals wear and filters load, so trend the differentials instead of waiting for alarms.
When a fan motor fails at night, the repair cannot wait for a change board, but the record must hold up. Contain and inform QA, repair like-for-like, raise the change the same day if it is one, assess impact on pressures, batches and the CCS, and record the requalification decision.
An SOP register should record, for each SOP, the owner, version, review date and every document it refers to. Humiley's template covers 536 SOPs across 20 departments. The cross-reference column tells a change control which documents a revision touches, and review dates keep superseded versions out of use.
EU GMP Annex 15 (2015) lists seven elements a validation master plan should cover. The summary of facilities and systems with their qualification status is the one inspectors use: last qualification, next requalification and open deviations, in one table rather than a paragraph of intent.
EU GMP Chapter 4 asks for regular document review but sets no interval; 2–3 years is a common choice. Write down the events that pull a review forward: change controls, CAPAs on the procedure, a new disinfectant, audit observations, new products. At the scheduled review, read the SOP against the room's change and deviation logs.