Company news from Humiley Group INC and technical notes on cleanroom HVAC, GMP validation, semiconductor environments and energy-storage engineering.

  • 780 articles

Everything

From the Humiley newsroom

85 articles tagged #Annex1.

To a semiconductor engineer, Grade C at ISO 8 in operation looks loose. EU GMP Annex 1 adds microbial limits: 100 CFU/m³ in air, 50 per settle plate over 4 hours, 25 per contact plate. Rooms wiped with sporicide need floors and joints a fab never had to clean, and a CCS that ties the choices together.

InsightRead

Periodic and event-driven requalification

A new AHU on a running suite moves the pressure cascade, so its event-driven requalification reaches the differential at every door it serves. Change control sets that scope. Annex 1 (2022) separately caps periodic cleanroom intervals at 6 months for Grade A and B and 12 for C and D.

InsightRead

At 20 air changes an hour, a material airlock needs about 14 minutes for a 100:1 particle drop after the outer door closes. The interlock needs a hold-open timer and alarm for trolleys, and the countdown should start at door closure. The gowning airlock is laid out around people instead.

InsightRead

Annex 1 initial validation of an aseptic process needs at least 3 consecutive successful simulations covering all working shifts, then periodic runs twice a year per process, line and shift. The cleanroom must hold its qualified state throughout. Agree an HVAC freeze date with QA, and list in advance which jobs are like-for-like and which need an impact assessment.

InsightRead

WHO's 2022 GMP for sterile products (TRS 1044, Annex 2) follows EU Annex 1. For a WHO-prequalification plant the barrier comes first: a RABS needs a Grade B background, a closed isolator Grade D, and that sets the HVAC. The contamination control strategy should be written alongside the design.

InsightRead

PIC/S GMP and EU GMP: who issues the certificate

The PIC/S GMP Guide and EU GMP are almost identical, revised Annex 1 included. In the EU the GMP principles are set in law and certificates sit in EudraGMDP; PIC/S authorities adopt the guide nationally and PIC/S certifies nothing. One design serves both; the EU inspection route is planned separately.