The installed HEPA scan covers media, frame and the filter-to-housing seal, but not the flange between housing and ceiling. Where the ceiling void runs at higher pressure than the room, unfiltered air enters there. Seal it with an evenly compressed gasket and sealant bead, then probe the flange and file the result.
Set a cleanroom pressure alarm delay from OQ recordings: log each door opening at one-second resolution, use the longest normal recovery plus margin as the floor and the risk assessment as the ceiling, record the justification per room pair, and add a separate door-held-open alarm.
The pressure drop at which a supply AHU's final filters are changed should be the dirty-filter allowance the fan was selected for at design stage, checked at FAT and quoted in the maintenance task. Raise it later and room pressure drifts down inside its alarm band, visible only on the trend.
When a terminal label disagrees with the drawing, fault-finding turns into guessing. At FAT, trace ten random wires end to end, read device tags against the drawing and bill of materials, and confirm the door-pocket drawing carries the same revision as the equipment file. After site changes, return marked-up drawings.
When a desiccant rotor loses its reactivation heater it keeps turning and soon stops drying. Control reactivation from the dew point leaving the rotor, alarm rotor rotation separately from the drive motor, write the heater-trip response into the URS, and time the dew point rise with a deliberate trip at OQ.
A single differential gauge across several AHU filter stages cannot say which stage loaded, so teams change everything or guess. A gauge per stage, marked with the commissioning reading and change limit and kept on the calibration list, allows each stage to be changed on condition. BMS transmitters add a trend.
An FFU array can average 0.45 m/s and still have a corner at 0.30 m/s. Measure each unit on a grid at FAT with fan speed settings recorded, then repeat the grid across the installed array at OQ. A flat map is healthy; a low edge points at speed, plenum, blanking or lights.
EN 1886 classes AHU casing strength by deflection at test pressure: D1 up to 4 mm/m, D2 up to 10 mm/m. On a high-static GMP supply unit, a flexing panel works its gaskets loose and leakage rises. Ask which class was tested, on what model box, and whether your design pressure fits.
A spring isolator with its transport bolt still fitted transmits everything. Remove transport locks, select isolators for the lowest drive speed, keep flexible connections slack, remove rigid bridges such as conduit or drain lines, use inertia bases where needed, and file the balance report and a vibration baseline.
An AHU's section split and weight are set by the tightest point on its delivery route: door clear openings, lift car and rated load, corridor corners, crane reach and floor loading. Survey the route before the general arrangement is frozen, and plan a casing leakage check after site reassembly.
A failed acceptance criterion and a protocol step not executed as written are different OQ deviations. The first needs root cause, impact assessment, a fix and a repeat test; the second needs an assessment of whether the result still stands. Changing a criterion after a failure invites audit questions.
A 100 cm² door gap at 15 Pa passes about 110 m³/h, but only doors on the suite boundary cost fresh air. Internal door leakage returns through the neighbouring room's grille. For twenty doors with four on the boundary, the leakage to make up is 440 m³/h rather than 2,200 m³/h of wet tropical air.