A 0–10 V transmitter where the IO list says 4–20 mA passes a visual FAT and fails on site. That and four more defects (missing tags, gasket gaps, drain pans that hold water, missing documents) are worth checking at every AHU FAT against the approved specification and IO list.
A pass box exists for its interlock: one door stays locked until the other is shut. Each side needs an indicator showing why, a dynamic box should show when purge time has run, and the locks' behaviour on power failure must be decided in the risk assessment and tested at OQ.
On the suction side of the fan, any casing leak between the final filter and the fan draws unfiltered plant-room air into the supply. On the pressure side leaks blow outward and the filter catches what the fan sheds. The cost is a plenum, and the filter bypass class still needs specifying in either layout.
An AHU condensate line piped directly into a floor drain gives backed-up water and sewer gas a route to the unit. Each AHU needs its own trap, then a visible air break into a tundish or trapped gully, sized to the local plumbing code. The gap also shows anyone passing whether condensate is running.
A pressure gauge shows filter loading but not a collapsed bag, a slipped gasket or a wet drain pan. Viewing windows and internal lights in the filter, coil, humidifier and fan sections let technicians check with the unit running. Double-glaze windows on cold sections, and keep the doors for checks that need a stop.
Heat of adsorption and carry-over from the regeneration sector warm the air leaving a desiccant rotor. Size the post-cooler on rotor leaving temperature at full duty, treat it as a dry sensible coil, control room temperature on it and humidity on the rotor, and check the chilled water it needs.
Most first-start damage to an AHU comes from something left inside or left bolted. Remove transit fixings, test insulation, bump the fan for rotation, run at low speed, then read current, vibration and bearing temperature before ramping to duty and recording the static pressure profile as the baseline.
Pressure readings that jitter when a fan changes speed often trace to the cable between drive and motor. Use screened symmetrical motor cable, bond the screen all round at both ends, keep it out of the signal tray, and stay within the drive's maximum cable length or fit an output filter.
A panel that passed its factory test has since been transported, lifted and cabled. Before the incomer is closed: inspect inside and check torque marks, measure and record insulation resistance, compare protection settings with the coordination study, prove earth continuity and phase rotation, and confirm tools are out and covers on.
An H14 filter is rated for particles, at least 99.995% at the most penetrating particle size, and its leak test uses an aerosol. Solvent vapour passes through it. Vapours and gases need adsorption or scrubbing sized for the compound, or, where emission limits allow, a once-through exhaust discharged away from intakes.
A cleanroom door that opens towards the lower pressure is pushed off its seal: 15 Pa on a 0.9 m by 2.1 m leaf is about 28 N. WHO's HVAC guideline says swing doors should normally open to the high-pressure side. Where escape rules differ, choose the closer for the pressure and justify the exception.
Default drive parameters will run an AHU fan but may not restart it after a power dip. Set the motor nameplate data, run the motor identification, set speed limits and ramps, add skip bands where the unit resonates, then decide and test behaviour on power loss, signal loss and fire mode. File the parameter list.