Many potent suites recirculate through safe-change HEPA housings; where the risk assessment rules that out, every cubic metre is tropical outdoor air. Run-around coils recover heat with the airstreams fully separated, wheels open a leakage path, and dedicated fresh-air pre-cooling targets the latent load. Our energy modeling targets a 30% HVAC energy reduction.
EN 1822 classifies a filter at its rated airflow. Above it, pressure drop rises roughly in proportion to media velocity, diffusion capture falls and the most penetrating particle size shifts smaller. A filter classed H14 at nominal flow may not reach H14 efficiency at 120% of it.
A mechanical completion certificate records static checks: built as drawn, pressure and leakage tested, cables tested, punch items sorted. Starting fans needs a separate ready-for-commissioning certificate, signed by the commissioning lead, covering flushing, cleanliness, calibration, interlocks and approved procedures, so the rooms are walked before first start.
H14 filters capture at least 99.995% at the most penetrating particle size, but that rating is measured on the element in a factory. On a potent-compound exhaust, an unseated gasket or leaking frame bypasses it. The exhaust housing needs test access designed in and an installed leak test in qualification.
AHU casing classes such as L1 leakage or TB2 thermal bridging usually come from a standard EN 1886 model box. The unit on site has more doors, joints and penetrations. At FAT, check them on the real unit, especially filter frame gaskets: bypass around the fine-filter frames loads the terminal HEPA filters faster.
Contractor self-commissioning is cheaper but lacks distance; an independent commissioning agent costs a fee and works for the owner. QA needs independence only on the results it will rely on: pressure cascade, air change rates, HEPA leak tests, alarms and interlocks. The rest can be self-commissioned and spot-checked.
Under EN 1822, every filter from H13 upwards is tested individually and ships with its own report. At receiving, match class, serial number, rated airflow and result on label and report, then record each serial against its ceiling position in the IQ so a later leak-test failure can be traced to its lot.
A filter that passed its factory scan can still fail the installed leak test at the frame. Gel-channel grids seal without clamp force and allow quick changes; gasket grids depend on even clamping and take a compression set. Gel usually suits Grade A and B; gaskets can suit Grade D.
The installed HEPA scan covers media, frame and the filter-to-housing seal, but not the flange between housing and ceiling. Where the ceiling void runs at higher pressure than the room, unfiltered air enters there. Seal it with an evenly compressed gasket and sealant bead, then probe the flange and file the result.
In a potent-compound suite, open powder handling makes the room the primary containment; an isolator or closed transfer moves most of it to the equipment. Write the exposure limit into the URS in µg/m³, not only the OEB band, and ask for surrogate powder test data to set against it.
A single differential gauge across several AHU filter stages cannot say which stage loaded, so teams change everything or guess. A gauge per stage, marked with the commissioning reading and change limit and kept on the calibration list, allows each stage to be changed on condition. BMS transmitters add a trend.
A new AHU on a running suite moves the pressure cascade, so its event-driven requalification reaches the differential at every door it serves. Change control sets that scope. Annex 1 (2022) separately caps periodic cleanroom intervals at 6 months for Grade A and B and 12 for C and D.