An AHU casing is described by five EN 1886 classes: strength D1–D3, leakage L1–L3, filter bypass up to F9, thermal transmittance T1–T5 and thermal bridging TB1–TB5. A witnessed FAT can test leakage on the real unit; transmittance and bridging come from a laboratory model box, so the model box report belongs with the offer.
A depyrogenation tunnel runs from the wash room into a Grade B filling room, across one or two grade steps, and releases heat next to the Grade A zone. Its own airflow balance and heat release per zone belong in the design basis, and the rooms are balanced with the tunnel at temperature.
A V-belt sheds rubber dust into the airstream for its whole life, and in a GMP supply AHU that dust loads the final filters. Belt drives also lose a few per cent of shaft power and need regular tensioning. Direct-drive plug fans avoid all three, though a large belt-driven housed fan can still win at high pressure.
When a supply AHU trips with extract fans running and dampers open, a Grade B room loses its 10–15 Pa margin and pulls air from the lower grade. Tight-shutoff dampers with a tested leakage class, defined fail positions, interlocks, proven position and a supply-first restart keep the cascade, and a deliberate fan trip at FAT proves it.
A full-size 592 × 592 mm bag filter is commonly rated at about 3,400 m³/h. A 20,000 m³/h AHU needs six frames; a casing with room for four runs each at 47% over, with higher pressure drop, possibly lower efficiency and fluttering pockets. The frame count belongs in the specification and the FAT.
21 CFR 11.10(e) says record changes shall not obscure previously recorded information. A SCADA log that stores only the new setpoint fails on that phrase. Three tests before OQ: read the trail after a change, try to edit it as administrator, and compare its retention with the batch records.
A fixed-speed fan filter unit loses airflow as its HEPA filter loads. Set at 0.45 m/s, it has 20% to lose before the 0.36 m/s bottom of the Annex 1 guidance range. Constant-airflow EC units hold velocity if they are selected at the final pressure drop, and their speed trend doubles as a filter-loading record.
A 0–10 V transmitter where the IO list says 4–20 mA passes a visual FAT and fails on site. That and four more defects (missing tags, gasket gaps, drain pans that hold water, missing documents) are worth checking at every AHU FAT against the approved specification and IO list.
One fume hood with a 1.8 m sash open 0.5 m at 0.5 m/s exhausts about 1,620 m³/h, or 9 air changes an hour in a 180 m³ lab. Variable-volume hoods save energy when sashes close, but their tracking has to be tested by failing a sensor at commissioning.
A pass box exists for its interlock: one door stays locked until the other is shut. Each side needs an indicator showing why, a dynamic box should show when purge time has run, and the locks' behaviour on power failure must be decided in the risk assessment and tested at OQ.
An AHU condensate line piped directly into a floor drain gives backed-up water and sewer gas a route to the unit. Each AHU needs its own trap, then a visible air break into a tundish or trapped gully, sized to the local plumbing code. The gap also shows anyone passing whether condensate is running.
Most first-start damage to an AHU comes from something left inside or left bolted. Remove transit fixings, test insulation, bump the fan for rotation, run at low speed, then read current, vibration and bearing temperature before ramping to duty and recording the static pressure profile as the baseline.