Run-to-failure is a valid maintenance strategy only when a failure shows at once. Standby pumps, fire dampers and smoke detectors fail silently and never qualify. For the rest, check GMP impact, replacement cost and restore time, then record each decision in the criticality assessment with its reason.
Check the cascade room by room: doors should open into the higher-pressure room, BMS setpoints should match the drawing, EMS alarm limits and delays should match the CCS, and each pressure transmitter should measure the rooms the drawing names. Record every difference before deciding which side is wrong.
A Class II type B2 cabinet exhausts all of its air, so room supply must follow it on and off and the exhaust fan needs an alarm and interlock. An A2 exhausts around 30% and, on a canopy, barely moves the balance. Choose B2 only when volatile chemicals demand it.
Moving a room pressure setpoint from 15 Pa to 12 Pa changes nothing physical and still changes a qualified parameter. Annex 15 section 11 and Annex 11 put it under change control: raise it, assess the cascade and the CCS, decide on retest, then edit. Lock qualified setpoints behind a controlled role.
In a GMP air handling unit, a wheel carries some exhaust into the supply by design, and a purge sector only reduces it. Run-around coils keep the streams apart at lower recovery. Plate exchangers leak in the direction the fan positions set, so mark and measure the pressure on each side before and at commissioning.
A liquids suite is washed down often, so its contamination points are floor drains, floor falls, floor-wall joints and purified water outlets. Falls must reach the drain without ponding, drains must be cleanable, joints coved, outlets drainable and sampled, and airflow sized to dry the room before the next shift.
ISO 14644-1 sets class limits at six particle sizes, and ISO 7 has limits at only three: 352,000 at ≥0.5 µm, 83,200 at ≥1 µm and 2,930 at ≥5 µm per m³. A URS that states the class without the size and occupancy state leaves both to the protocol writer.
ISO 14644-1 allows a room to be classified as-built: installation complete, services running, no equipment, materials or people. On a new suite it shows whether the HVAC, filters and envelope can reach the class alone. It says nothing about machines or people, so the GMP classification is still done at rest and in operation.
FDA's 2004 aseptic guidance asks for at least 10–15 Pa between rooms of different classification; Annex 1 gives at least 10 Pa as guidance. Setting each cascade step at 15 Pa meets both. Holding it is harder: seals wear and filters load, so trend the differentials instead of waiting for alarms.
In unidirectional airflow at 0.45 m/s, a 28.3 L/min particle counter needs an inlet about 37 mm across to sample isokinetically, and a 100 L/min counter about 69 mm. An undersized inlet draws air in too fast, large particles miss it by inertia, and the ≥5 µm count reads low.
When a fan motor fails at night, the repair cannot wait for a change board, but the record must hold up. Contain and inform QA, repair like-for-like, raise the change the same day if it is one, assess impact on pressures, batches and the CCS, and record the requalification decision.
An SOP register should record, for each SOP, the owner, version, review date and every document it refers to. Humiley's template covers 536 SOPs across 20 departments. The cross-reference column tells a change control which documents a revision touches, and review dates keep superseded versions out of use.