Cooling coils foul on the air-entering face, while water and growth appear on the leaving side over the drain pan. A hygienic AHU needs access sections upstream and downstream of the coil and a sloped, reachable drain pan that extends past the leaving face.
A 12-months-from-commissioning or 18-months-from-delivery warranty, whichever ends first, shrinks when the building is late. An AHU delivered in March and started in November keeps only ten months of cover. Tie the start to commissioning, get storage instructions in writing, and keep the storage log that makes a claim possible.
A pass box sits across a grade boundary designed for at least 10 Pa. The interlock does not fix a worn door seal, a static box is made safe by the disinfectant contact time rather than by waiting, and a dynamic box needs its supply balanced against both rooms and its HEPA filter leak tested.
Standing condensate in an AHU drain pan sits upstream of the final filters. ASHRAE 62.1 asks for a pan sloped at least 10 mm per metre toward the outlet so it drains completely. Check the slope with a level at FAT, prime the trap after long shutdowns and inspect the pan on a schedule.
Voltage distortion is harmonic current multiplied by source impedance. An EC fan wall draws the same harmonic current on grid or generator, but a transformer is typically 4–6% impedance and a generator's subtransient reactance typically 12–20%. Model both sources and set a distortion limit for the busbar on standby power.
EU GMP Chapter 4 asks that any alteration is signed and dated, leaves the original readable and records a reason where appropriate. Correction fluid, overwritten digits and blacked-out entries all break that rule and ALCOA+. Engineering and site teams need it in their induction as much as QA.
A weekly FMEA review earns its time only when it ends in decisions. Ask the same five questions every week: what is new, which scores moved and why, who owns each open risk, what the next action is and when, and what can be closed on evidence.
A calibration certificate that expires partway through air balancing leaves the later readings without a traceable instrument at OQ review. Before commissioning, list every instrument that will produce a qualification reading, check each due date against the whole test window plus slippage, and record the serial on every test sheet.
Grade A must meet ISO 5, 3,520 particles of 0.5 µm or larger per cubic metre, both at rest and in operation. An FFU array is therefore judged with operators and machines in the zone: uniform unidirectional flow, leak-tested H14 filters and a smoke study run with the real interventions.
IQ should start from a verified installation. Before a turnover package moves from construction to qualification it needs a marked boundary, every IQ-blocking punch item closed, commissioning and balancing results, walked-down as-builts, calibration certificates and the equipment file. If one is missing, the package goes back.
EU GMP Annex 15 allows some FAT results to be used at IQ and OQ when transport and installation do not affect them. For an AHU that means listing what the trip can change, from fan alignment to software version, retesting those on site and referencing the rest.
A loaded filter sheds part of its dust cake when the clamps release. Withdraw it through the upstream access section or sideways through a casing door, never through the section behind it. Then check every clamp by hand and log the new filter's differential pressure as the baseline.