A shared exhaust duct spreads a solvent's hazardous zone, cakes process dust in humid air, carries potent-compound contamination through the building if joined upstream of the HEPA, and moves fume-hood face velocity with other dampers. Draw each stream with its hazard, treatment and fan first.
A failed acceptance criterion and a protocol step not executed as written are different OQ deviations. The first needs root cause, impact assessment, a fix and a repeat test; the second needs an assessment of whether the result still stands. Changing a criterion after a failure invites audit questions.
Air leaving a coil at 12 °C and 95% RH reads about 50% RH at 22 °C with the same 8.3 g/kg of water. A duct RH sensor after the coil works at the top of its scale. Control the coil on dew point or leaving-air temperature, and keep duct RH after reheat as a wet-filter alarm.
A pre-filter changed at 150 Pa on a 0–1,000 Pa gauge sits in the bottom 15% of the dial with about 20 Pa of uncertainty. A 0–250 Pa gauge puts it at 60% with 5 Pa. Range each stage's gauge and transmitter to its own change point.
A 15–25 °C store in Viet Nam needs active cooling. Split units give cheap N+1 redundancy but a short air throw and little humidity control. A chilled-water AHU ducts air to the top of tall racking and can control dew point, with dearer redundancy. Humidity limits on the labels usually decide it.
A 3 m/s supply jet near a pressure tap can shift the reading by up to about 5 Pa, down or up depending on its angle, which is a third to half of a 10–15 Pa cascade. Tap position, tubing without low loops, matched tube lengths and a still reference port decide whether a room pressure trend is trustworthy.
When deviations, change control and EM trends live in different systems, one event can carry three dates. Rehearse the first-hour inspection requests by pulling all seven records for one day six months back, then check that each system gives the same date and cross-reference for it.
A 100 cm² door gap at 15 Pa passes about 110 m³/h, but only doors on the suite boundary cost fresh air. Internal door leakage returns through the neighbouring room's grille. For twenty doors with four on the boundary, the leakage to make up is 440 m³/h rather than 2,200 m³/h of wet tropical air.
An AHU casing is described by five EN 1886 classes: strength D1–D3, leakage L1–L3, filter bypass up to F9, thermal transmittance T1–T5 and thermal bridging TB1–TB5. A witnessed FAT can test leakage on the real unit; transmittance and bridging come from a laboratory model box, so the model box report belongs with the offer.
A dry-room door opening onto the plant room swaps about 2 m³ of air at 20 g/kg, bringing in roughly 48 g of water. A −40 °C room supplied at −50 °C needs about 730 m³ of supply air to absorb it. Airlocks with their own dry supply, interlocked doors and counted door-open time follow from that sum.
A depyrogenation tunnel runs from the wash room into a Grade B filling room, across one or two grade steps, and releases heat next to the Grade A zone. Its own airflow balance and heat release per zone belong in the design basis, and the rooms are balanced with the tunnel at temperature.
Annex 1 expects the Contamination Control Strategy to be actively reviewed and updated. A yearly meeting catches changes late. Adding one question to every HVAC change control, EM adverse trend review and deviation closure form, asking whether the CCS still says the right thing, keeps it current with the site.