WHO's 2022 GMP for sterile products (TRS 1044, Annex 2) follows EU Annex 1. For a WHO-prequalification plant the barrier comes first: a RABS needs a Grade B background, a closed isolator Grade D, and that sets the HVAC. The contamination control strategy should be written alongside the design.
A spring isolator with its transport bolt still fitted transmits everything. Remove transport locks, select isolators for the lowest drive speed, keep flexible connections slack, remove rigid bridges such as conduit or drain lines, use inertia bases where needed, and file the balance report and a vibration baseline.
Heating 18 °C, 60% RH air to 22 °C drops the reading to about 47% RH while the air keeps 7.7 g of water per kilogram. A room that meets RH only on reheat has no margin for one fault. Trend reheat output beside room RH: rising reheat means the coil is losing latent capacity.
A passing floor and passing heel grounders do not prove the operator is grounded. IEC 61340-5-1 and ANSI/ESD S20.20 treat the path from person to ground as a system, with a wrist strap system below 35 MΩ. Qualify footwear and flooring together, then check ionisers, garments and the RH band.
21 CFR 11.10(e) requires secure, computer-generated, time-stamped audit trails. For an environmental monitoring system, that means the software logs setpoint, alarm-limit and user changes itself, nobody can purge entries, every clock follows one time source, and the requirements sit in the URS before a platform is chosen.
Annex 1 leaves Grade B particle monitoring frequency and sample size to the site. A sequential counter with 8 one-minute ports revisits each point about every 8 minutes, so a 3-minute event can be missed. Set locations from the smoke study, frequency from the events, and justify both in the CCS.
An AHU's section split and weight are set by the tightest point on its delivery route: door clear openings, lift car and rated load, corridor corners, crane reach and floor loading. Survey the route before the general arrangement is frozen, and plan a casing leakage check after site reassembly.
Cartons and labels from an 80% RH warehouse release moisture in a 20% RH packing room. If board gives up 2% of its weight, a 500 kg delivery adds 10 kg of water. Stage packaging in a controlled area, unwrapped, for a time set by weighing sample cartons.
Each kilogram of electrolytic hydrogen needs at least 9 kg of water, and at 75% RO recovery that means 12 kg of feed. Pharma water habits such as sampling plans, trended conductivity and buffer storage transfer well. A WFI-style loop may not: build to the electrolyser supplier's feedwater specification.
A classified room's air change rate, recovery time and pressure steps were proved at one airflow. Constant volume holds each room's flow at that value with a terminal, while the fan speeds up as filters load. VAV moves supply with the cooling load, so it belongs in offices, technical areas and fume-hood exhaust.
The PIC/S GMP Guide and EU GMP are almost identical, revised Annex 1 included. In the EU the GMP principles are set in law and certificates sit in EudraGMDP; PIC/S authorities adopt the guide nationally and PIC/S certifies nothing. One design serves both; the EU inspection route is planned separately.
Put containment exhaust fans at the end of the run so ducts inside the building stay negative. Run duty and standby with isolation dampers and alarmed changeover, discharge vertically with height and velocity from a standard or a dispersion study, and keep the plume away from fresh-air intakes.